Skip to content
MSc. Stefan Paskalovski

Electrical engineering consultant for costed technical decisions

Power System Consultant — Technical & Financial Consulting

Power system consultant and electrical engineering consultant in Macedonia, combining technical and financial assessment.

Download PDF

Focus

  • Technical evaluation
  • Cost analysis
  • Engineering consulting

Tools used

  • Microsoft Excel
  • Microsoft Word
  • Engineering documentation

Key objectives

  • Assess technical feasibility

  • Analyze equipment and system requirements

  • Estimate project costs

  • Support decision-making with structured analysis

Approach

  1. 01

    Review project requirements

  2. 02

    Perform technical analysis

  3. 03

    Evaluate financial aspects

  4. 04

    Compare alternative solutions

  5. 05

    Provide structured recommendations

Consulting scope

As a power system consultant, the work starts from the network: configuration, equipment, protection and the standards the project has to meet. As an electrical engineering consultant in Macedonia, the same review includes cost, so a technically sound option is not chosen if a simpler one meets the requirement.

Technical analysis

Key technical aspects evaluated:

  • Power system configuration
  • Selection of electrical equipment
  • Protection systems and reliability
  • Compliance with engineering standards
  • System performance and efficiency

Financial analysis

Evaluation of project costs and financial aspects:

  1. Equipment cost estimation
  2. Installation and commissioning costs
  3. Operational considerations
  4. Budget planning and cost optimization

Analysis balances technical performance and cost efficiency: selection of cost-effective equipment, optimization of electrical schemes, evaluation of alternative solutions, and risk versus cost comparison. The benefit is reliable system performance with optimized investment cost.

Case study: substation equipment selection (110/35 kV)

SS Skopje 1 110/35 kV substation project.

Parameter Option A (standard) Option B (optimized)
Transformer 40 MVA 31.5 MVA
Protection scheme Basic (50/51) Advanced (50/51 + 87T)
Switchgear Conventional Compact GIS
Estimated cost €280,000 €240,000
Reliability Medium High

Analysis: Option B provides better protection and system reliability. The lower transformer rating was optimized based on load analysis. Overall cost is reduced with improved performance.

Decision: selected Option B for an optimal balance between cost and reliability.

Financial breakdown and optimization

Estimated cost structure of the same substation project:

Cost category Estimated cost % of total
Power transformer €120,000 40%
Switchgear €80,000 27%
Protection system €25,000 8%
Installation & commissioning €50,000 17%
Engineering & documentation €25,000 8%

Equipment sizing was reviewed against real load requirements. The protection scheme was optimized to avoid overdesign. Installation costs were balanced with the project timeline.

Decision: reduced unnecessary investment, maintained required technical performance, and improved cost efficiency of the project.

Protection settings that come out of this kind of review are applied under relay protection testing and coordination. Installation design is covered under electrical installation design and testing.